Porch Demolition - Day 3

The rain stopped and the porch removal project started back up. The remaining floor and joist sections were cut apart and removed. All that remains is the brick foundation which will be removed sometime during the next week or so.





On Thursday the contractor finished firring the remaining ceilings that will be drywalled.

Wednesday, March 28, 2007

Rainy Day

It rained all day today which put the porch removal project on hold. Moving inside for the day, the contractor attached fir strips to the ceilings in three rooms. All of the rooms except the front foyer and the upstairs hallway will have new drywall ceilings.



Tuesday, March 27, 2007

Porch Demolition - Day 2

Today was day two of the porch removal. The only things remaining are the first floor decking and brick foundation.



Monday, March 26, 2007

Porch Demolition - Day 1

The contractor started on the demolition of the back sleeping porch. The roof and second floor walls were all taken down during day one. Here are some pictures of the days progress.


Sunday, March 25, 2007

March 25th Update

We continue to work on the plaster walls and foyer ceiling. We spent most of the time at the house this weekend working on the front two bedrooms. As we've said in the last several posts, we're making progress but there's still a lot to do.

The HVAC subs were back this week to finish hooking up the heat pumps. We now have heat and AC on both the first and second floors. They're done for now but will be back when the porch section is framed in.

Sunday, March 18, 2007

Slow News Week

You'll be disappointed to hear that there isn't a lot to report this week. We pretty much did the same things that we've been doing for the past several weeks...plaster repair. At least the finish line is in sight for the wall repairs. With the exception of the the two upstairs front bedrooms, we're more or less done with joint compounding for now. We'll probably have more touch up work after we start sanding.

Although there is little news in the land of renovations, we'd like you to know that there is peace in our animal kingdom.

Wednesday, March 14, 2007

Dumpster Vol. 2

We had a second dumpster dropped off for all of the plaster and other demolition junk that's piled up since we had the first dumpster. We'll also need it for the upcoming removal of the back porch section that's being replaced.



Monday, March 12, 2007

March 12th Update

During the past week a lot of work has been done at the house. The contractor framed in the two new closets in the front two bedrooms. The electricians have done the rough in wiring for about 85% of the existing house. We now have temporary lights in all of the rooms except the kitchen and several working electrical outlets.


We plan to use reproduction push button switches for all of the downstairs switches and the upstairs hallway switch.


All of the outside walls are plaster on brick which makes it hard to install wall outlets. Because of this a lot of the electrical and cable outlets will have to be in the floor.


We continue to work on fixing the plaster walls and front foyer ceiling. We've made a lot of progress but there's still a lot more to do.

Monday, March 05, 2007

March 5th Update

This past week the contractor and electricians were back at work wiring the second floor electrical panel in the attic and the second floor rooms. We now have lights in the attic and temporary lights in several of the bedrooms.



We continue to work on the plaster repairs throughout the house. It's slow going but we are making progress. Here are some pictures from the front entrance room.


Sunday, February 25, 2007

How Far We've Come....

We've never previously posted a cluster of the "before" pictures in order to avoid horrifying our family and friends or risking long-term, involuntary commitment to a local mental health facility. Given our progress, it is now time to show you (as opposed to describing) just how awful it really was. It's even stunning to us how bad it actually looked.

Here's what you are seeing...in no particular order since the blog site is not cooperating with easy photo posting today:
Foyer fireplace and pile of tenant's junk;
Upstairs hallway and pile of tenant's junk;
Hall bathroom and pile of tenant's junk;
Master bedroom and giant pile of tenant's junk;
Small front bedroom and more junk (note the kerosene heater and canister of kerosene!!);
Rear bedroom (the green peeling wallpaper and mold photo...blech!);
And last but not least....the kitchen.





More Wall Repairs

As usual, we were back at the house this weekend for more repair work. We continued working on the dining room walls, spent some time on the ceiling in the foyer, and did some touch up on walls that are pretty close to complete (except for sanding).


Here is one of the walls in the dining room. There is an earlier picture of this wall in last week's post. Not to sound like a broken record, but the joint compound looks a hundred times better than the nasty brown paint.


Here's a before and after comparison of the foyer. The first picture was taken when the tenant was still "living" in the house and before we even made an offer. Just looking at this picture is nauseating. The second picture was taken this afternoon. No more nasty wallpaper, wall stains or giant holes in the plaster. And most importantly, no more horrid stench.



We are exceptionally proud of the wall repair in the picture below. This wall is on the right side of the foyer and just below the stairs. A lot of the plaster was crumbling and stained. First, we scraped all of the loose plaster off and applied giant pieces of mesh wall tape. Next, we applied layer after layer of joint compound and ended up with a repaired wall. As we've experienced with some of the other walls, some of the yellow stains seep into the joint compound as it dries. We'll use a primer, such as Kilz, to stop this after we sand and are ready to paint.